15.1. Lecture exercise#
Note
The calculations serve as examples for educational purposes and not as guidance for practice.
Note
This exercise shows some of the basic principles of an LCA. It serves educational purposes and should not be used for guidance in practice. The lecture, which covered this example, was given in the course Sustainable Construction Members in the Master Civil Engineering, track Structural Engineering, by Henk Jonkers in the academic year 2023-2024.
Goal#
Calculate ECI value for materials (LCA module A1-A3) used for construction and transportation (LCA module A4) and construction processes (LCA module A5) of a concrete water reservoir (thus construction phase only), and determine which input variable (material or process) contributes most to the construction stage ECI value, and give advice on options on how the ECI value can possibly be decreased.
Data#
The necessary materials and processes of the required LCA modules are given in Table 15.1.
Inputs |
Quantity |
Unit |
Distance |
Unit |
Required Quantity |
Unit |
---|---|---|---|---|---|---|
Concrete |
7.56E+05 |
[kg] |
7.56E+05 |
[kg] |
||
Steel |
1.73E+04 |
[kg] |
1.73E+04 |
[kg] |
||
Sand |
1.20E+05 |
[kg] |
1.20E+05 |
[kg] |
||
Truck mixer |
3.15E+02 |
[m^3] |
45 |
[km] |
1.42E+04 |
[m^3*km] |
Lorry |
1.73E+01 |
[ton] |
125 |
[km] |
2.17E+03 |
[ton*km] |
Welding casting |
2.88E+02 |
[h] |
2.88E+02 |
[h] |
The impact categories per materials and process are given in Table 15.2.
Inputs |
Unit |
GWP |
HTP |
AP |
---|---|---|---|---|
Concrete |
[kg] |
0.0921 |
0.0102 |
0.0002 |
Steel |
[kg] |
1.79 |
3.81 |
0.0074 |
Sand |
[kg] |
0.0025 |
0.0017 |
0.0001 |
Truck mixer |
[m^3*km] |
0.22 |
0.04 |
0.0013 |
Lorry |
[ton*km] |
0.13 |
0.038 |
0.0007 |
Welding casting |
[h] |
43.3289 |
27.4484 |
0.3335 |
Total shadow costs are set to the following per unit of input:
GWP: € 0.05
HTP: € 0.09
AP: € 4.00
Questions#
1 What is the total (construction) environmental cost (ECI value) of the concrete water reservoir?#
Solution
By multiplying the materials and processes data from Table 15.1 with Table 15.2 and its corresponding shadow costs, the costs per material/process can be calculated, displayed in Table 15.3.
Inputs |
Unit |
EUR/input |
GWP |
HTP |
AP |
---|---|---|---|---|---|
Concrete |
[kg] |
€ 4,780.19 |
0.0921 |
0.0102 |
0.0002 |
Steel |
[kg] |
€ 8,004.15 |
1.79 |
3.81 |
0.0074 |
Sand |
[kg] |
€ 81.36 |
0.0025 |
0.0017 |
0.0001 |
Truck mixer |
[m^3*km] |
€ 280.67 |
0.22 |
0.04 |
0.0013 |
Lorry |
[ton*km] |
€ 27.55 |
0.13 |
0.038 |
0.0007 |
Welding casting |
[h] |
€ 1,719.59 |
43.3289 |
27.4484 |
0.3335 |
The total costs can now be summed and amount to € 14,893.50.
2 Which two inputs (materials or processes) contribute most to the total environmental impact?#
Solution
Steel the most, concrete 2nd
3 Suggest two measures which can be taken to lower the impact most effectively?#
Solution
Make a more efficient design that creates less tensile forces, thereby requiring less reinforcement steel
Use another form of concrete, geopolymer concrete